METHODOLOGY
The Road Safety Audit Team was established as follows:
Skip: Interactive content (iframe)
The interactive content below might not be fully accessible.
-
The Audit was undertaken after detailed examination of the submitted documents, and a visit to the site on 3 August 2017 between 14h00 to 16h30 (daylight) and 19h00 to 20h20 (night-time). The weather was warm and clear with occasional overcast conditions. The road surface was dry.
-
The Road Safety Audit was undertaken on the project, detailed in the following documentation:
-
-
No details about P21-1 were received from the client
-
Drawing nos. | Ver | Title |
No detail construction drawings No as built drawings No Line marking drawings |
No departure from standards was submitted to the Audit Team.